The short version
Santa Monica city staff want to open exclusive talks with Cypress Equity Investments over seven city-owned parcels on the 1600 block of 5th Street, between Colorado Avenue and Olympic Boulevard, next to the Downtown Santa Monica E Line station. Cypress has offered a base price of $30.25 million, rising to as much as $35 million if certain development conditions are met. Its plan calls for 301 affordable apartments built without a city subsidy, plus a self-storage building of about 96,000 rentable square feet.
The City Council takes up the item on Tuesday, Nov. 17, as part of its consent calendar. The Santa Monica Lookout first reported the recommendation on Nov. 12, and Santa Monica Next covered it the same day. A yes vote would not sell the land. It would start a negotiating period that could lead to a sale agreement next year.
How the 5th Street lots got here
The site covers about 1.85 acres. It includes Parking Lot 29 and the so-called Apple Building at 1636 5th Street, plus the Kiss and Ride lot at the Expo terminus. According to the city staff report, the council declared the parcels surplus in three votes between 2021 and 2024, and the state Department of Housing and Community Development confirmed on Nov. 4, 2024 that the city had followed the Surplus Land Act.
This is the city's second try. In 2023 the council approved exclusive talks with AMCAL Multi-Housing and Gen-Land, a firm tied to Lincoln Property Company, for a mixed-use project of about 570 homes. The Lookout called it a record proposal at the time. The city ended those talks in July 2024 after staff concluded the project was financially infeasible.
Cypress was in that earlier round too. The Santa Monica Daily Press reported in 2023 that Cypress was eliminated from contention after it lowered its purchase offer to account for building a minimum amount of affordable housing.
After the AMCAL deal ended, the Kiss and Ride lot served as a temporary home for Palisades Charter High School after the January 2025 Palisades Fire, a use that ran into early 2026. The city then went back to market with a request for letters of interest issued May 20, 2025.
What Cypress is offering
Staff say the city received six proposals, with prices ranging from $7.3 million to $38 million. They rated each on price, affordable units, financing, developer experience and timing. Three made the final cut: AMCAL, Cypress and Lincoln Property Company.
The main terms of the Cypress offer, as laid out in the staff report:
- Price: $30.25 million base, potentially rising to $35 million if specified conditions are met.
- Housing: 301 affordable units, with no city subsidy.
- Other use: a self-storage facility of roughly 96,000 net rentable square feet.
- Deposit: a good-faith deposit of 3% of the base price, or $907,500, refundable during a 90-day feasibility period and nonrefundable after that, subject to negotiated exceptions.
- City costs: a separate $50,000 deposit to cover the city's costs of reviewing and negotiating the deal.
- Timing: 18 to 36 months to reach permit-ready status, with closing within 30 days after permits are ready.
The Lookout adds detail from the proposal. It reports the plan as two seven-story buildings on separate legal parcels, with the 301 apartments split into 148 one-bedroom, 77 two-bedroom and 76 three-bedroom units. The staff report does not explain how the storage building fits into the project's finances, and neither news outlet reported Cypress's reasoning.
How the deal tools work
Three pieces of state housing finance shape this deal.
The Surplus Land Act. California requires cities to offer surplus public land to affordable housing builders first. HCD's fact sheet on the law says agencies must negotiate in good faith for at least 90 days with interested developers who propose at least 25% affordable housing, and priority goes to the proposal with the most affordable units. If land sells for housing without such a deal, at least 15% of the units must be affordable to lower-income households. Santa Monica staff say they will confirm that 15% minimum during talks with Cypress. HCD keeps its notices and compliance reviews on its surplus land page.
The 4% tax credit. Cypress expects to use California's 4% Low-Income Housing Tax Credit for part of the financing. The California Tax Credit Allocation Committee awards 4% credits on a non-competitive basis, but only to projects that also win tax-exempt bonds. Those bonds are handed out competitively by the California Debt Limit Allocation Committee. Because the bond step is competitive, staff flagged tax credit availability as a term they may need to revisit.
The exclusive negotiating agreement. The agreement would give Cypress six months of exclusive talks, with one six-month extension if both sides agree. During that time Cypress would do its due diligence, and the city would test the financing plan, expected tax credits, proof of financial capacity, schedule and closing conditions. Staff also list open items that include the EVgo charging license on the site, parcel configuration, community engagement and development milestones.
The other bids and what is still unknown
The Cypress pick is not the highest bid. The Lookout reports that AMCAL offered $38 million for a 428-unit project with 64 affordable units, and Lincoln Property Company offered $23 million for 372 units with 54 affordable units. Staff wrote that AMCAL's limited financing information raised questions about feasibility and certainty of delivery, and that Lincoln's offer came with conditions requiring city policy commitments.
Staff are also candid about Cypress. The firm reports more than 1,000 homes in its Santa Monica pipeline, including 506 under construction. Staff say that experience supports its capability, but that "the feasibility of the proposed City Properties development remains to be established." The city plans to reassess price, financing and terms against current financing costs, tax credit availability, and expected materials and labor costs.
There is recent history behind that caution. In September 2025 Cypress walked away from its approved 521-unit project at the Gelson's site on Lincoln Boulevard. The Lookout reported that the company blamed the decision in large part on Measure GS, the 2022 transfer tax on Santa Monica property sales above $8 million. The same report pointed to high interest rates and an uncertain economy, and said only 181 of more than 4,300 approved units in the city had building permits at that point. The 5th Street plan is all affordable and leans on tax credits rather than market-rate rents, so its math is different, but it shows approved projects in Santa Monica can still stall.
No public opposition to the agreement had been reported as of Nov. 13. The item sits on the consent calendar, which means the council can approve it without discussion unless a member pulls it.
Why Santa Monica wants affordable units here
The city's 2021 to 2029 housing element assigns Santa Monica 8,895 new homes for the cycle, and 6,168 of them, about 69%, are for very low, low and moderate income households. The document itself says the funding gap makes the affordable portion of that target unrealistic without much more money. A 301-unit, fully affordable project on publicly owned land next to a rail stop would count toward that goal without city subsidy, if it gets built.
What happens next
- Nov. 17, 2026: the City Council votes on whether to authorize the agreement. Staff also ask the council to find the step exempt from environmental review, since it approves no construction.
- First 90 days after signing: Cypress's feasibility period, when its $907,500 deposit stays refundable.
- Six to 12 months: the exclusive negotiating window, including the optional extension.
- After talks end: staff would bring a purchase and sale agreement back to the council, along with any budget actions. The project itself would need separate environmental review.
- 18 to 36 months: Cypress's estimate to reach permit-ready status, with the land sale closing about a month after that.
What it means for LA agents
- Expect new rental supply near Downtown Santa Monica, but not soon. Even if every step goes smoothly, construction would not start until permits are ready, which Cypress puts 18 to 36 months out.
- Watch the 4% credit pipeline. Bond and credit awards drive whether big affordable projects get built across LA County. When a project like this wins or loses a bond allocation, it is a useful signal for buyers and investors weighing nearby rentals.
- Public land is a source of housing sites. The Surplus Land Act requires cities and counties to offer surplus lots to housing builders first. Clients who own property next to a surplus parcel should know what may rise next door.
- Keep Measure GS in mind on big Santa Monica sales. Cypress cited the transfer tax on deals above $8 million when it dropped the Gelson's project. It matters for sellers of larger apartment and commercial properties in the city.
- Follow the Nov. 17 vote and the purchase agreement that follows. Price, unit count and the storage component can all change during talks.